Completed:
Ward School drainage site work, tile 12 rooms
Ward School boilers
Columbus: boilers
Webster: boilers
NRHS: McKenna Field
Davis: Playground
Jefferson: Playground
Not Completed (est. date)
Trinity playground (8/28/2008)
NRHS HVAC (9/1/2008)
New Rochelle High School GC & EC, dehumidify, painting, tile, doors, benches, decking, lights, clocks, PA system (9/1/2008)
Albert Leonard Middle School PA system, clocks, auditorium lighting (12/31/08)
IYMS HVAC system, refurbish auditorium & gym (9/1/2008)
IYMS 2 boilers (9/15/2008)
Barnard café ventilation & floor, lights, pave rear parking, refurbish auditorium (9/1/2008)
Davis refurbish audit, seats, lights, carpet, curtains, sound system, acoustic panels, replace exterior doors (9/15/2008)
Trinity replace entire roof in original wing (9/1/2008)
Trinity 30 ceilings, lights, PA, clock instructional areas (9/1/2008)
Trinity replace electrical switch gear, PA , clock non-instructional (10/1/2008)
Jefferson replace entire roof & masonry pointing (8/29/2008)
Jefferson windows (summer 2009)
Ward lobby curtain walls, 5 exterior doors (9/15/2008)
Emergency Projects
NRHS Slate Roofs & Façade Masonry, new North Tower roof & masonry repairs on entire façade (10/15/2008)
NRHS Auditorium Ceiling,acoustically engineered (8/31/2008)